Lukut-Kampung Sirusa Road Project Ahead of Schedule at 60.57% Completion
A RM81.92 million infrastructure project linking Lukut and Kampung Sirusa in Port Dickson has surpassed the midway mark with 60.57% completion and is tracking 43 days ahead of schedule.